Riverstone Wastewater Treatment Plant
All Case Studies
Water Industry Riverstone, NSW

Riverstone Wastewater Treatment Plant

Stage 1 Amplification & Upgrade

3 Yrs
Project Duration
Zero Harm
Safety Record
LSCTP
Program of Works
01
Engaged
LSCTP Program
Contract awarded
02
Mobilised
Riverstone
On-site delivery
03
Delivered
3 Years
Total programme
04
Outcome
Zero Harm
Safety standard met
Project Summary

Stage 1 Amplification & Upgrade

AJM United worked with UGL and other contractors to deliver the first of three major projects on the LSCTP (Lower South Creek Treatment Program). Despite complex challenges, AJM United built a reputation for on-time delivery, high-quality standards, and achieving Zero Harm throughout. The team managed tight window shutdowns and worked against the clock to complete scopes without affecting plant operations.

Key Achievements

Milestones engineered into delivery.

Quantifiable wins from a programme delivered to the highest engineering, safety and environmental standards.

3 Yrs
Project Duration
Zero Harm
Safety Record
LSCTP
Program of Works
Specialist Water Industry
Sector-specific expertise applied end-to-end
01 — Challenge

The Challenge.

The project had many challenges — tight window shutdowns required working against time to ensure scope of works were completed within the timeframe or risk affecting plant operations. Coordination between AJM United and the client UGL required high-quality standard compliance with zero compromise on health, safety, and environment.

Riverstone Wastewater Treatment Plant — on-site delivery
On-site · Riverstone
02 — Coverage

Areas of Work.

  • Inlet Processing Area (Screenings & Grit Removal/Handling)
  • Mechanical Primaries Area
  • MPS Primary & Secondary Channels
  • Polymer Dosing Plant
  • Liquid Sugar Storage and Dosing
  • Primary Sludge Gravity Thickeners
  • Digester Gallery
  • Digester Feed Well Tank
In The Field

Project Gallery.

A visual window into the water sector environments AJM United operates within.

Wastewater treatment plant works
Wastewater treatment plant works
Water recycling facility
Water recycling facility
Sewerage infrastructure upgrade
Sewerage infrastructure upgrade
On-site civil construction
On-site civil construction
Plant maintenance scope
Plant maintenance scope
04 — Outcome

Delivered. Safely. On time.

Delivered on time. Zero harm achieved. Reputation established as the go-to SMP subcontractor on the LSCTP program, leading to subsequent award of further projects on the same program.

Ready to discuss your project?