Central Station Rail Works
All Case Studies
Rail Industry Central Station, Sydney CBD — 27m below ground

Central Station Rail Works

Sydney Metro — Structural Steel Supply & Installation

12 Days
Platform 12 Possession Window
27m
Below Ground Level
Zero Harm
Zero Incidents
01
Engaged
Sydney Metro
Contract awarded
02
Mobilised
Central Station
On-site delivery
03
Delivered
2 Years
Total programme
04
Outcome
Zero Harm
Safety standard met
Project Summary

Sydney Metro — Structural Steel Supply & Installation

AJM United were engaged by Laing O'Rourke on Sydney Metro's largest project — Central Station. The underground station sits approximately 27 metres below ground level within the existing Central Station precinct. AJM United delivered multiple scopes across a project vast in scale, variety of hazards, and tight time constraints.

Key Achievements

Milestones engineered into delivery.

Quantifiable wins from a programme delivered to the highest engineering, safety and environmental standards.

12 Days
Platform 12 Possession Window
27m
Below Ground Level
Zero Harm
Zero Incidents
Specialist Rail Industry
Sector-specific expertise applied end-to-end
01 — Challenge

The Challenge.

Every task required precise planning with detailed Construction Methodologies and Safe Work Method Statements (SWMS), given the presence of the general public, live train lines, and high-voltage overhead power lines. The most critical milestone was the capping beam possession for Platform 12: the entire project team had just 12 days to demolish the existing platform, excavate, construct the capping beam, install new hoarding, and fit all platform equipment to allow public access on New Year's Eve.

Central Station Rail Works — on-site delivery
On-site · Central Station
In The Field

Project Gallery.

A visual window into the rail sector environments AJM United operates within.

Rail infrastructure project
Rail infrastructure project
Rail engineering works
Rail engineering works
Steel fabrication for rail
Steel fabrication for rail
Rail maintenance shutdown works
Rail maintenance shutdown works
04 — Outcome

Delivered. Safely. On time.

Possession milestone achieved. Laing O'Rourke handed over to Sydney Trains and opened Platform 12 for New Year's Eve as planned. Delivered on time and on budget. Zero injuries or incidents — AJM United's ZERO Harm KPI maintained throughout the entire project.